Kırıkkale · 2018 – 2021
Samsung Kırıkkale IPP
Co-Plus treatment control system at a natural gas combined cycle power plant
At the treatment plant of a natural gas combined cycle power plant, operator-dependent fixed dosing was replaced with measurement-based automatic dosing, and stable floc formation was achieved for the first time.
About the Project
At the treatment plant of the Samsung Kırıkkale IPP natural gas combined cycle power plant, dosing and process control depended on operator intervention, and fixed dosing could not keep up with variable flow and pollution load.
The Co-Plus system, working with turbidity, flow, pH and conductivity measurements, was installed together with PLC automation and an HMI panel showing real-time values and alarms. It was commissioned in stages without interrupting power generation.
Dosing and equipment control became measurement-based, and stable floc formation was observed at the plant for the first time. Process parameters and interventions are now recorded and can be reported.
- Client
- Samsung Kırıkkale IPP
- Location and date
- Kırıkkale · 2018 – 2021
- Sector
- Energy
- Sensors
- Turbidity, flow, pH, conductivity
- Software / hardware
- Co-Plus, PLC automation, HMI panel (real-time values and alarms)